5 t/hDR Congo·2026–present
Matadi 5 TPH Spray-Tower Detergent Plant
Buyer-side project engineer
Leading the technical side of a new 5 t/h high-spray-tower detergent powder plant with a 12 t/h post-blending mixer (~700 t of equipment). Scope covers plant layout, civil conditioning drawings, material selection (carbon vs. stainless steel), 3D model review, dosing parameters and manufacturing/inspection follow-up with the Chinese supplier.
Several plantsGuinea·2022–present
Detergent Plants Supervision, Guinea
Technical supervisor
Supervision of several detergent manufacturing plants: process troubleshooting, formulation adjustment and production efficiency.
Full greenfield designAngola·2019–2022
Complete Factory Design, Ecochemico
General Manager
Designed the complete factory infrastructure (process, MV/LV power, IT) and all products, formulas and artworks; increased spray-tower capacity and implemented raw/packaging material tracking across the supply chain.
Loss → profitAngola·2018–2019
New Bleach Process, Africa Future
Chief Operating Officer
Designed a new on-demand bleach (lixívia) production process and revamped the product formulas, turning the operation from loss to profit.
3.5 → 5.5 t/hAngola·2013–2018
Spray-Tower & Chlorine Capacity Upgrade, Basel Angola
Plant Manager
Raised spray-drying tower output from 3.5 to 5.5 t/h, increased chlorine section capacity to 200 t/day, and redesigned the liquids section with flexible piping and mixers.
GreenfieldSyria·2022–2024
Juice Factory from Scratch, Syrjuice
General Manager
Designed and implemented a complete juice factory: MV/LV/IT infrastructure, equipment installation, product development, formulas, branding and packaging artwork.
−70% lighting energySyria·2011–2013
Energy-Saving Projects, Alresala / Milkman
Plant Manager
Delivered a solar water-heating project for the boiler section, cut lighting electricity by 70% with LED retrofits, redesigned milk chilling to 4 °C, refurbished a 1.5 L PET filling line and rebuilt the IT network with 160 IP cameras.
DCSSyria·2009–2010
Spray Tower & DCS Operations, Al Namaa
Drying Tower / Manufacturing / IT Manager
Ran the detergent-powder spray tower and manufacturing, maintained the plant's Distributed Control System and managed the company IT infrastructure.
Ballestra labSyria·2001–2008
Petrochemical Plant Infrastructure, Daaboul Group
Infrastructure Project Manager
Built the multi-site data network for the group, led infrastructure (data, telephony, fire alarm, lightning and earthing networks) for a petrochemical plant, computerized a Ballestra-sponsored lab and designed three industrial-PC-driven printing machines.
Siemens S7 · HMISyria / Africa·Ongoing
Industrial Automation & Control Panels
Control & automation engineer
Design of control panels on Siemens S7 PLCs with external HMI touch screens, plus rehabilitation of legacy PLC/SCADA systems on detergent spray-drying plants.
Fuel savingAfrica·
Burner Efficiency: Water-in-Diesel Emulsion
Process engineer
Engineering analysis of diesel burners on spray-drying towers and application of water-emulsion injection to cut fuel consumption and emissions.
6 product familiesSyria / Angola·Ongoing
Formulation R&D Across Industries
Formulation developer
Development of production-ready formulas for detergents, cosmetics, paints, PVAc white glue, liquid sodium silicate and bleach, with packaging specs and artwork (e.g. 25 ml essential-oil bottles) and production-line design for chemical and potato-chips plants.
3 t/h·
Industrial Wood-Chipping Machine (3 TPH)
Procurement & technical lead